Redco Jinan Future City commercial project

Release time :2024-01-05 10:01:14   Views:
Project start date: November 27, 2021
Project Location: West side of Jinger Road, south side of Weier Road, Jiyang District, Jinan City, Shandong Province
Scope of BIM implementation: above-ground commercial, basement

Project Overview: The Redco Future City project will build a high-quality complex complex project with large-scale comprehensive commerce, star-rated hotels, and artificial intelligence research and development and display as the main body, integrating science popularization, culture, entertainment, catering, and shopping.
BIM application point: three-dimensional laser scanning technology is used to scan the point cloud of the building structure, the point cloud model is combined and compared with the BIM model, and the inspection report is generated; the BIM technology is used to create the BIM model of each discipline according to the two-dimensional construction drawings and detect the collision problem between the disciplines; the quality of the drawings is effectively controlled, and the rework, demolition and modification caused by the design conflict between the disciplines are avoided in the construction process, and the construction cost is effectively reduced.

Project Scale:
Project scale: 18822.74m2
Total construction area: 92886.8m2
Above-ground construction area: 65722.58m2
Underground construction area: 27164.22m2


1. BIM model
(Civil Model)

(Electromechanical model)
 
2. Construction phase
Use three-dimensional visualization to guide on-site construction

3. Inspection stage
Merge and compare the on-site point cloud model with the BIM model, check whether the site is constructed according to the construction drawings, and generate an inspection report